I-580 construction pushes on



Cathleen Allison/Nevada Appeal<br /> Construction on the 8.5 mile I-580 freeway project continues Friday as crews, using a 500-foot-long conveyor, move dirt to backfill over the temporary arch over Galena Creek. The contractor will have to move 4 million cubic-yards of dirt to aid in the construction of the 700-foot arches in the middle of the 1,725-foot-long bridge. The project is expected to be completed in 2011.
Cathleen Allison/Nevada Appeal<br /> Construction on the 8.5 mile I-580 freeway project continues Friday as crews, using a 500-foot-long conveyor, move dirt to backfill over the temporary arch over Galena Creek. The contractor will have to move 4 million cubic-yards of dirt to aid in the construction of the 700-foot arches in the middle of the 1,725-foot-long bridge. The project is expected to be completed in 2011.ENLARGE
Cathleen Allison/Nevada Appeal
Construction on the 8.5 mile I-580 freeway project continues Friday as crews, using a 500-foot-long conveyor, move dirt to backfill over the temporary arch over Galena Creek. The contractor will have to move 4 million cubic-yards of dirt to aid in the construction of the 700-foot arches in the middle of the 1,725-foot-long bridge. The project is expected to be completed in 2011.
Work continues on the $394 million I-580 Highway project from Reno to Carson City.

The project has a total of nine bridges including the 1,719-foot long, 300-foot high Galena Creek bridge in Pleasant Valley. That structure accounts for nearly $95 million of the total $393.4 million contract and has been the subject of significant controversy.

The original bridge contractor, Edward Kraemer & Sons, was terminated after saying they didn't think it would be possible to safely erect the bridge because of wind conditions at the site.

The new bridge contractor, C.C. Myers of Sacramento, plans instead to fill in the Galena Creek valley with dirt to support the concrete arch as it is poured in place, then remove the dirt and restore the area.

NDOT Spokesman Scott Magruder has said altogether, it will take nearly four years to complete what is, to date, the largest single highway contract in Nevada history.

When finished, he said most of the 40,000 cars that drive between Reno and Carson City every day will move off the old road through Pleasant Valley onto the new freeway, eliminating about 70 percent of the traffic on Highway 395 in Pleasant Valley.