Road Report for Oct. 18-24

  • Discuss Comment, Blog about
  • Print Friendly and PDF

The following Road Report applies to the period of October 18-24:

The Roop Street widening project is continuing and is expected to be completed by the end of 2010. The following impacts are expected this week:

• Roop Street is now open between William Street and Robinson Street. Roop Street will have intermittent lane restrictions from Robinson Street to Washington Street for striping.

• William Street will have intermittent lane closures at Roop Street on Monday - Friday, 9 a.m.-7 p.m. for westbound traffic.

• Long Street will be closed from Stewart Street to Marian Street. Traffic will be detoured via Stewart Street, Corbett Street, and Molly Drive.

• Lee Street and Beverly Drive will be closed to through traffic at Roop Street. All Senior Center traffic should utilize Beverly Drive from the east via Marian Avenue, Molly Drive, and Corbett Street.

• Roop Street is closed from William Street to Stewart Street through the completion of the project.

As a result of the next phase of the NDOT project on the freeway, Koontz Lane will be closed between Raglan Circle and Edmonds Drive until January 2011.

Due to water utility improvements, the following activity is expected:

• Hells Bells Road between Parkhill Drive and Marsh Road will be closed to through traffic (local traffic allowed) all week.

• Butti Way will be reduced to one lane between Airport Road and Fairview Drive with flaggers during daytime hours.

• Construction will continue near the intersection of Northridge Drive and Russell Way for the Fulstone Wetlands Enhancement project. Work will be off-street, but there may be occasional delays due to construction activity. Please use caution.

Comments

Use the comment form below to begin a discussion about this content.

Sign in to comment